Run Number: 00006450

Summary information for each of the Warehouse Refresh Cycle processes performed during the run is provided below.


Process Start Date and Time End Date and Time Status
WH01 - SAMS Transaction Detail Extract 08/30/2021 08:08 PM 08/30/2021 08:10 PM WH01 COMPLETED
WH02 - SAMS Reference Table Update 08/30/2021 08:08 PM 08/30/2021 08:08 PM WH02 COMPLETED
WH03 - BOND TRANSACTIONS 08/30/2021 08:23 PM 08/30/2021 08:23 PM PROCESS COMPLETE
WH03 - CONTRACT HEADERS 08/30/2021 08:21 PM 08/30/2021 08:21 PM PROCESS COMPLETE
WH03 - CONTRACT LINES 08/30/2021 08:21 PM 08/30/2021 08:21 PM PROCESS COMPLETE
WH03 - NON-COMM TRANSACTION VENDOR 08/30/2021 08:08 PM 08/30/2021 08:08 PM PROCESS COMPLETE
WH03 - NON-COMM WARRANT HEADER UPDATE 08/30/2021 08:08 PM 08/30/2021 08:08 PM PROCESS COMPLETE
WH03 - NON-COMM WARRANT LINE APPEND 08/30/2021 08:08 PM 08/30/2021 08:08 PM PROCESS COMPLETE
WH03 - PURCHASER PAYMENTS - EXPENDITURES 08/30/2021 08:21 PM 08/30/2021 08:21 PM PROCESS COMPLETE
WH03 - TRANSACTION APPEND - BUDGET 08/30/2021 08:19 PM 08/30/2021 08:19 PM PROCESS COMPLETE
WH03 - TRANSACTION APPEND - EXPENDITURES 08/30/2021 08:19 PM 08/30/2021 08:21 PM PROCESS COMPLETE
WH03 - TRANSACTION APPEND - REVENUES 08/30/2021 08:21 PM 08/30/2021 08:21 PM PROCESS COMPLETE
WH03 - TRANSACTION UPDATE APPROPRIATIONS 08/30/2021 08:19 PM 08/30/2021 08:19 PM PROCESS COMPLETE
WH03 - TRANSACTION UPDATE IOC PO ORDERS 08/30/2021 08:21 PM 08/30/2021 08:21 PM PROCESS COMPLETE
WH03 - TRANSACTION VENDOR 08/30/2021 08:10 PM 08/30/2021 08:11 PM PROCESS COMPLETE
WH03 - WARRANT HEADER UPDATE 08/30/2021 08:10 PM 08/30/2021 08:11 PM PROCESS COMPLETE
WH03 - WARRANT LINE APPEND 08/30/2021 08:11 PM 08/30/2021 08:11 PM PROCESS COMPLETE
WH03 - WH10 PVTX APPEND 08/30/2021 08:10 PM 08/30/2021 08:12 PM WH10 COMPLETED
WH03 - WH17 PREVAILING WAGE CONTRACTS 08/30/2021 08:10 PM 08/30/2021 08:10 PM WH17 COMPLETED
WH03 - WH17 PREVAILING WAGE TEXT 08/30/2021 08:10 PM 08/30/2021 08:10 PM WH17 COMPLETED
WH03 - WH17DLT DELETE PREV WAGE 08/30/2021 08:10 PM 08/30/2021 08:10 PM PROCESS COMPLETE
WH03 - WH19 PO TEXT 08/30/2021 08:23 PM 08/30/2021 08:23 PM PROCESS COMPLETE
WH04 - PAYMENT DETAILS 08/30/2021 08:35 PM 08/30/2021 08:36 PM PROCESS COMPLETE
WH04 - PAYMENT SUMMARY 08/30/2021 08:35 PM 08/30/2021 08:36 PM PROCESS COMPLETE
WH04 - SUMMARIZE BUDGET 08/30/2021 08:23 PM 08/30/2021 08:23 PM PROCESS COMPLETE
WH04 - SUMMARIZE EXPENDITURE BY APPROPRIATION 08/30/2021 08:25 PM 08/30/2021 08:27 PM PROCESS COMPLETE
WH04 - SUMMARIZE EXPENDITURE BY OBJECT 08/30/2021 08:24 PM 08/30/2021 08:25 PM PROCESS COMPLETE
WH04 - SUMMARIZE ISL OBJ EXP 08/30/2021 08:34 PM 08/30/2021 08:34 PM PROCESS COMPLETE
WH04 - SUMMARIZE ISL SUMMARY 08/30/2021 08:33 PM 08/30/2021 08:33 PM PROCESS COMPLETE
WH04 - SUMMARIZE REVENUE 08/30/2021 08:23 PM 08/30/2021 08:24 PM PROCESS COMPLETE
WH04 - SUMMARIZE VENDOR CONTRACTS 08/30/2021 08:29 PM 08/30/2021 08:33 PM PROCESS COMPLETE
WH04 - SUMMARIZE VENDOR EXPENDITURES 08/30/2021 08:27 PM 08/30/2021 08:29 PM PROCESS COMPLETE
WH05 - WARRANT STATUS UPDATE 08/30/2021 08:23 PM 08/30/2021 08:23 PM WH05 WARR STATUS COMPLETED